正解:A
This question fits the Process domain because it deals with issue resolution during execution. PMI's PMP Examination Content Outline emphasizes engaging stakeholders, managing issues, and ensuring that project work remains aligned with requirements and expected outcomes. When a critical performance issue is identified during implementation, the project manager should first collaborate with the relevant stakeholders to understand the issue, assess impact, and determine the appropriate resolution path. Stakeholder engagement is essential because performance issues often affect scope, acceptance, schedule, or business value.
Option B is too narrow and may be only one input to the analysis. Option C delegates the matter away instead of leading coordinated resolution, although SMEs may later support the solution. Option D may eventually be required if the resolution changes baselines, but PMP-style thinking does not jump straight to a change request before the issue is assessed and discussed with the right stakeholders. The project manager should first work collaboratively to define the problem and response, then use formal change control if needed. That makes stakeholder-based issue resolution the best initial action.