開発フェーズの終わり近くに、ビジネス アナリスト (BA) に、同じリリースの一部としてシステムに組み込む必要がある追加要件が与えられます。このような状況では、提案された変更の影響を理解するために BA が実行する最初のアクティビティは次のようになります。
正解:C
Comprehensive and Detailed The BA mustfirst determine whether the additional requirement is traceable to a legitimate business need, ensuring that it is justified before assessing feasibility. BABOK Guide (Chapter 5.1 - Trace Requirements)states that all requirements should belinked to business needs, objectives, and stakeholder requirementsbefore proceeding with implementation. Checking with the project manager (Option A)is necessary for feasibility but comes after traceability is established. Determining stakeholder availability (Option B)does not validate the need for the requirement. Consulting with the technical team (Option D)is important for feasibility but does not validate business need.