正解:A
When a feature is too large to fit into a sprint, agile recommendsdecomposing it into smaller user storiesor increments. According to thePMI Agile Practice Guide (Section 5.2: User Stories and MVPs)andMike Griffiths' PMI-ACP Exam Prep Book (Chapter 6: Adaptive Planning), teams should break down epics or large stories intoMinimum Viable Product (MVP)segments and deliver value incrementally.
* Option Ais correct: this enables the team to deliver value sooner and iteratively build on it.
* Option Bdelays addressing customer concerns.
* Option Csacrifices overall product balance.
* Option Dviolates time-boxing principles in Scrum and agile.