You need to determine when to release resources from your project. Which part of the staffing management plan will be most useful for this?
正解:B
One of the most important elements of the staffing management plan is the timetable, which tells you who will work on what, and when they will be released from the project. One of the most common ways of showing the timetable is the resource histogram (or staffing histogram). That timetable will let you know exactly when you plan to release your project resources.