You are project manager responsible for constructing a new sports arena for the upcoming Olympics. Construction began on a project over a year ago. The stakeholders of the project want a status report on the performance of the project to date. You've obtained the following measurements: BAC=500, ETC=200, PV=500, AC=200, EV=300, CPI=1.5 You believe the type of variances that have occurred on the project to date are typical, and do not expect these variances to continue. What is the VAC for the project?