You are project manager of ABC company and you have to choose one project between two of them. Which of the following factor you would NOT cosider for the project selection?
正解:D
Option A, B and C all are project selection factor. < li >Net present value (NPV): The present value of cash inflow less the present value of cash outflow. A negative NPV is unfavorable; the higher the NPV, the better. < li > Opportunity cost: The difference in benefit received between a chosen project and a project that was not chosen < li >Payback period: The number of time periods required until inflows equal, or exceed, costs. The lower the payback period, the better