An intentional activity to ensure future performance of project work is aligned with the project management plan is______________
正解:A
Explanation/Reference: Explanation: As a specific subset of change requests, approved preventive actions are an input to the direct and manage project work process. Such actions are intentional to ensure the future performance of the project work is aligned with the project management plan.