正解:B
The project manager should review the requested change first to assess its impact, feasibility, and alignment
with the project objectives and scope. Reviewing the change will help the project manager to determine if the
change is necessary, beneficial, and acceptable to the stakeholders. The project manager should also consider
the risks, costs, and quality implications of the change before proceeding to the next steps of the change
management process123. References = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter
9: Project Change Management, p. 323; 5 Steps in the Change Management Process | HBS Online; 8 Steps for
an Effective Change Management Process - Smartsheet