正解:D
The project manager should use a change control log to document the effects of the hurricane delay on the
project. A change control log is a tool that records and tracks any changes that occur during the project
lifecycle. It usually includes information such as change ID, description, impact, status, approval, and
resolution. A change control log can help to monitor and manage the changes that affect the project scope,
schedule, cost, quality, or resources and ensure that they are aligned with the project objectives and
stakeholder expectations.