正解:A
According to the PMBOKGuide, specifically within the Estimate Costs process, the accuracy of a project estimate increases as the project progresses through its life cycle.
* Rough Order of Magnitude (ROM): This type of estimate is typically provided during the Initiating phase of a project when very little detail is known.
* The Range: A ROM estimate is historically defined with an accuracy range of -25% to +75%. However, in various versions of the PMI standards and exam contexts, a range of +/- 50% is frequently used to represent the high level of uncertainty during the earliest stages of the project.
* Evolution of Estimates: As more information becomes available through the Planning phase, the estimate is refined into a Definitive Estimate, which typically has a much narrower range, such as -5% to +10%.
* Analysis of Other Options:
* B. In the Planning phase, the estimate is in the range of +/- 50%: Incorrect. By the planning phase, the team is working toward a " Budget Estimate " (-10% to +25%) or a " Definitive Estimate. "
* C and D. Monitoring and Controlling / Closing: Estimates are updated during these phases, but the term ROM specifically refers to the " rough " figures used at the start of the project to determine feasibility, not the refined data used during execution or closing.