正解:B
According to the PMBOKGuide, specifically within the Control Costs process of Earned Value Management (EVM), forecasting involves estimating the future financial performance of the project based on the information available at the time of the evaluation.
When a sponsor asks for the forecast of the total project cost at completion, the metric used is the Estimate at Completion (EAC).
* Definition: The EAC is the expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
* Purpose: While the Budget at Completion (BAC) tells you what you planned to spend, the EAC tells you what you are actually likely to spend by the time the project is finished, given the current performance trends (CPI and SPI).
* Calculation: There are several ways to calculate EAC depending on whether the current variances are seen as typical or atypical, but the most common " forecasting " formula is:
$$EAC = \frac{BAC}{CPI}$$
(This formula assumes that the project will continue to perform at the same cumulative Cost Performance Index encountered to date.) Analysis of other choices:
* Choice A (BAC - Budget at Completion): This is the total planned budget for the project. It is a static baseline and does not account for actual performance or overruns; therefore, it is not a " forecast. "
* Choice C (ETC - Estimate to Complete): This represents the expected cost to finish all the remaining work. It is only a portion of the total cost. To get the total project cost, you would need to add the Actual Cost (AC) to this figure ($EAC = AC + ETC$).
* Choice D (WBS - Work Breakdown Structure): This is a hierarchical decomposition of the total scope of work. While it is used to build the budget, it is a planning tool, not a mathematical forecasting metric.