正解:B
According to the PMBOK Guide, projects are initiated in response to factors that influence an organization.
These are often categorized as Project Initiation Contexts. One of the primary reasons is Market Demand.
* Market Demand: This occurs when a change in the marketplace, consumer behavior, or the economy creates a need for a new product or service.
* The Scenario: In Option B, a gasoline shortage represents a significant shift in market conditions.
Consumers will naturally seek vehicles that cost less to operate, creating a " demand " for fuel efficiency. The company initiates the project specifically to capture this market opportunity.
* Other Initiation Contexts:
* Strategic Opportunity/Business Need: High-level goals of the organization.
* Social Need: Improving the well-being of a community.
* Environmental Considerations: Projects aimed at sustainability or conservation.
* Legal/Regulatory Requirements: Projects mandated by new laws.
* Technological Advance: Using new tech to improve products.
Analysis of Other Options:
* A. A public company authorizes a project to create a new service for electric car sharing to reduce pollution: This is primarily driven by Environmental Considerations or Social Need. While there may be a market for it, the stated intent (reducing pollution) aligns with sustainability goals rather than a reaction to market demand.
* C. Researchers develop an autonomous car with several new features to be commercialized in the future: This is an example of a project initiated due to Technological Advance. The researchers are pushing the boundaries of what is possible, which may create a market later, but the project itself is driven by innovation.
* D. Stakeholders request that raw materials be changed due to locally high costs: This is typically handled through a Change Request or an operational adjustment. If it were a project, it would be driven by a Business Need to improve profitability or reduce costs, rather than a demand from the external market for a specific product.