正解:D
In accordance with the PMBOKGuide and the Practice Standard for Work Breakdown Structures, the Work Breakdown Structure (WBS) is a fundamental tool used in the Create WBS process within the Scope Management knowledge area.
* Definition: The WBS is a deliverable-oriented hierarchical decomposition of the total scope of work to be carried out by the project team. It organizes and defines the total scope of the project.
* Hierarchical Structure: Each descending level of the WBS represents an increasingly detailed definition of the project work. The total of the work at the lowest levels must roll up to the higher levels so that nothing is left out and no extra work is performed (the 100% Rule).
* Purpose: It provides a structured vision of what has to be delivered. It serves as the framework for subsequent project management processes, including cost estimating, scheduling, and risk planning.
* Comparison with Other Options:
* Organizational Breakdown Structure (OBS) (A): This is arranged according to an organization ' s existing departments, units, or teams, with the project activities or work packages listed under each department. It shows which department is responsible for which work.
* Work Performance Information (B): This is the performance data collected from various controlling processes, analyzed in context and integrated based on relationships across areas.
* Work Package (C): This is the lowest level of the WBS. While it is part of the decomposition, it is the component of the WBS, not the hierarchical structure itself.