プロジェクトマネージャーは、多様な分野を扱う大手製造会社で働いています。プロジェクトチームは頻繁に変更要求に関与しています。最近、変更管理委員会(CCB)が一部の変更要求を延期したため、プロジェクトマネージャーはこれらの要求を関係者に伝えたいと考えています。プロジェクトマネージャーは、これらの要求を伝えるためにどのような文書を使用すべきでしょうか?
正解:B
A change log is a document that contains the list of changes that are made during the project. It tracks the progress of each change based on its review, approval, implementation, and closure. A change log is a useful tool for communicating the status of change requests to the stakeholders, as it shows the impact and outcome of each change. A risk log, a backlog, and an issue log are different documents that serve different purposes.
A risk log records the identified risks, their probability, impact, and response strategies. A backlog is a list of features or tasks that need to be completed in an agile project. An issue log records the issues that arise during the project, their causes, effects, and resolution. References:
* Change Log - Project Management Knowledge
* Change Log Template - Project Management Docs
* Risks, issues, and changes-help, I'm drowning in logs!