主要リスク指標 (KRI) がしきい値を超えていると定期的に上級管理職に報告されていますが、そのたびに上級管理職はリスクを軽減するための措置を講じないことを決定しています。上級管理職の対応の理由として最も可能性が高いのは次のどれですか。
正解:C
A key risk indicator (KRI) is a metric that measures the level and trend of a risk that may affect the organization's objectives, operations, or performance1. A KRI threshold is a predefined value or range that indicates the acceptable or tolerable level of risk for the organization2. Theorganization's risk appetite is the amount and type of risk that it is willing to take in order to meet its strategic goals3. Therefore, the most likely reason for senior management's response is that the KRI threshold needs to be revised to better align with the organization's risk appetite. This means that the current threshold is either too low or too high, resulting in false alarms or missed signals. By adjusting the threshold to reflect the organization's risk appetite, senior management can ensure that the KRI provides relevant and actionable information for risk management and decision making. The other options are not the most likely reasons for senior management's response, as they imply that the KRI is faulty, irrelevant, or misunderstood. The underlying data source for the KRI is using inaccurate data and needs to be corrected. This option assumes that the KRI is based on erroneous or unreliable data, which would affect its validity and reliability. However, this is not the most likely reason, as senior management would be expected to verify the data quality and accuracy before using the KRI for risk monitoring and reporting. The KRI is not providing useful information and shouldbe removed from the KRI inventory. This option assumes that the KRI is not aligned with the organization's objectives, strategies, or risk profile, which would affect its usefulness and value. However, this is not the most likely reason, as senior management would be expected to review and update the KRI inventory periodically to ensure that the KRIs are relevant and meaningful for risk management. Senior management does not understand the KRI and should undergo risk training. This option assumes that senior management lacks the knowledge or skills to interpret and use the KRI for risk management, which would affect their competence and confidence.
However, this is not the most likely reason, as senior management would be expected to have sufficient risk awareness and education to understand and apply the KRI for risk management. References = Risk and Information Systems Control Study Manual, 7th Edition, Chapter 2, Section 2.1.4, Page 53.