正解:A
The risk scenario chart shows the initial and residual risk ratings, and the project cost, for four projects named Sierra, Tango, Uniform, and Victor. The initial risk rating is the level of risk before applying any controls or mitigation measures, while the residual risk rating is the level of risk after applying the controls or measures.
The project cost is the amount of resources required to implement the project. These three factors can be used to determine the relative positions of the projects on a risk map, which is a graphical tool for displaying the risks based on their impact and likelihood. The risk map can help to prioritize and compare the risks, and to select the most appropriate risk response strategy. The other options are not the best answers, as they are not directly shown or derived from the risk scenario chart. The risk treatment options are the possible actions that can be taken to address the risks, such as accept, avoid, mitigate, or transfer. The capability of enterprise to implement is the ability of the organization to execute the risk response plan,considering the available resources, skills, and constraints. The multiple risk factors addressed by a chosen response are the various elements that contribute to or affect the risk, such as the threat sources, events, vulnerabilities, assets, and impacts. These factors are not explicitly stated or measured in the risk scenario chart, and may require further analysis or information. References = How to Write Strong Risk Scenarios and Statements - ISACA; Identifying the Right Risk Scenarios to Measure with FAIR; How to write good risk scenarios and statements