ある組織は、利害関係者が不在のため、いくつかのリスク シナリオの評価と処理を延期することを決定しました。この決定の結果、これらの新しいエントリに関連するリスクは次のようになりました。
正解:C
The result of postponing the assessment and treatment of several risk scenarios is that the risk associated with these new entries has been accepted. Risk acceptance is a risk response strategy that involves acknowledging the existence of a risk and deciding not to take any action to reduce its likelihood or impact. By postponing the assessment and treatment of the risk scenarios, the organization is implicitly accepting the risk and its consequences. Risk mitigation, deferral, and transfer are other possible risk response strategies, but they are not applicable in this case. References = ISACA Certified in Risk and Information Systems Control (CRISC) Certification Exam Question and Answers, question 9; CRISC Review Manual, 6th Edition, page 137.