アプリケーションは、複数のビジネス システムから財務データをコンパイルし、財務報告システムを更新するスケジュールされたジョブを実行します。このジョブの実行時間が長すぎると、財務報告が遅れる可能性があります。リスク担当者のベストの推奨事項は次のどれですか。
正解:D
The risk practitioner's best recommendation is to consider providing additional system resources to this job, as this would help to reduce the likelihood and impact of the risk of delaying financial reporting. Providing additional system resources, such as memory, CPU, disk space, or bandwidth, can improve the performance and efficiency of the application and the scheduled job. This can also help to avoid potential errors, failures, or interruptions that could affect the quality and timeliness of the financial data and reporting.
The other options are not the best recommendations for this situation. Implementing database activity and capacity monitoring is a good practice to identify and analyze the root causes of performance issues, but it does not directly address the risk of delaying financial reporting. Ensuring the business is aware of the risk is an important step to communicate and escalate the risk, but it does not provide a solution or mitigation strategy. Ensuring the enterprise has a process to detect such situations is a preventive measure to avoid or minimize the occurrence ofthe risk, but it does not eliminate or reduce the risk. References = Practical Recommendations for Better Enterprise Risk Management - ISACA, HR Risk Management: A Practitioner's Guide - AIHR, Isaca CRISC today updated questions - Verified by Isaca Experts