組織には、次のリスク軽減ポリシーがあります。
95%以上の確率のリスクは、影響に関係なく、他のすべてのリスクよりも先に対処されます。
他のすべての優先順位付けは、リスク値に基づきます。
組織は次のリスクを特定しました。

次のうち、リスク軽減の優先順位が最も高いものから最も低いもののどれですか?
正解:D
According to the risk mitigation policy, risks with a probability of 95% or greater will be addressed first, regardless of the impact. Therefore, risk D is the highest priority, as it has a probability of 95% and an impact of $100,000. The next priority is risk A, which has a probability of 90% and an impact of $200,000. The remaining risks will be prioritized based on their risk value, which is calculated by multiplying the probability and the impact. Risk C has a risk value of $40,000 (80% x $50,000), while risk B has a risk value of $30,000 (60% x $50,000). Therefore, risk C is higher priority than risk B.