正解:C,D
In SAP S/4HANA, an operation withDispatchedstatus (set in CM21 or PP/DS after scheduling) is assigned a fixed time slot on a work center. Options for rescheduling include:
* You can reschedule the operation using finite scheduling in a planning table(C): In the capacity planning table (CM21) or PP/DS Planning Board (/SAPAPO/CDPS0), you can manually drag-and-drop or use heuristics to reschedule a dispatched operation, respecting finite capacity constraints (work center, CR02, "Relevant to Finite Scheduling").
* You can reschedule the operation in the Manage Work Center Capacity app(D): This Fiori app (SAP GUI equivalent: CM25) allows planners to adjust dispatched operations' schedules by shifting them within available capacity slots, maintaining finite scheduling rules and updating the operation's time.
Lead time scheduling(A) (e.g., in CO02) recalculates the entire order's basic dates, not individualdispatched operations-it's not used post-dispatch.Infinite scheduling in a planning table(B) (e.g., ignoring capacity) isn' t typical for dispatched operations, which are already capacity-constrained. This is per SAP's dispatching options.