完成品の受注生産計画シナリオを設定したいと考えています。部品表には2つのコンポーネントが含まれています。1つは受注ごとに個別に調達し、もう1つはすべての独立所要量について一括調達する必要があります。完成品の予測は不可能です。これを実現するには、どのような設定が必要ですか?
正解:D
For a make-to-order (MTO) scenario in SAP S/4HANA without forecasting, where components have different procurement behaviors:
* Choose planning strategy 20 (Make-to-Order) and select the corresponding Individual/Collective indicator(D): Strategy 20 (material master, MRP 3 view, Strategy Group: 20) is pure MTO, where production is triggered by sales orders (VA01) without PIRs-fitting the "no forecasting" requirement.
TheIndividual/Collective indicator(material master, MRP 4 view, field: Ind./Coll.) is set to "1" (Individual Requirements) for the component procured per sales order, generating separate dependent requirements per order, and "2" (Collective Requirements) for the component procured jointly, aggregating requirements across all orders into a single planned order or requisition.
Planning strategy 50 (Planning without final assembly)(A, C) relies on PIRs for subassemblies, conflicting with the "no forecasting" condition.Mixed MRP indicator(B, C) (MRP 4 view) applies to mixed MTS/MTO scenarios (e.g., strategy 11), not pure MTO, and doesn't address the individual/collective split directly.
Strategy 20 with the indicator meets SAP's MTO configuration standards.