アジャイル プロジェクトは、2 週間の期間で 3 回目のイテレーションを実行しています。予測に関する経歴しか持たない新しいオペレーション ディレクターが会社で働き始めました。プロジェクト マネージャーとの最初の会議で、ディレクターはプロジェクトの状況を毎週報告するよう要求しました。
プロジェクトマネージャーは何をすべきでしょうか?
正解:C
In an agile project, communication is key, and it's important to educate stakeholders on the agile process.
The project manager should introduce the agile aspect to the director, explaining how agile projects differ from predictive ones, particularly in terms of reporting and project tracking. Agile projects typically use live reporting tools and methods like burn-down charts, backlogs, and user stories to track progress, rather than traditional status reports. By introducing these concepts to the director, the project manager can help them understand the agile environment and work together to find a reporting solution that fits within the agile framework and satisfies the director's need for information.
: The answer is verified with the PMP Examination Content Outline, which emphasizes the importance of stakeholder engagement and communication1. The explanation is supported by the PMBOK Guide standards, which detail the agile practices and the importance of adapting project management practices to the development approach2. Additionally, the Professional in Business Analysis Reference Materials highlight the significance of stakeholder communication and the use of agile tools for project tracking3.