The project manager should first revisit the project charter and assess if the project goals and objectives can be met with other alternatives. This could include re-evaluating the project requirements, researching other suppliers and/or re-designing the project in order to reduce the cost. If all other alternatives are exhausted, then the project manager should seek approval from the project sponsor or the CEO to proceed with the purchase order.