最近の事業売却により、組織は重要なプロジェクトを実施するための IT リソースが限られています。将来のプロジェクトのリソース要件を見積もる際に、IT 管理を最も適切に導くのは次のどれですか。
正解:B
The best source of information for IT management to estimate resource requirements for future projects is the records of actual time spent on projects. This data can provide a realistic and reliable basis for forecasting future resource needs based on historical trends and patterns. The records of actual time spent on projects can also help IT management to identify any gaps or inefficiencies in resource allocation and utilization. The human resources (HR) sourcing strategy is not a good source of information for estimating resource requirements for future projects, as it may not reflect the actual demand and availability of IT resources. The peer organization staffing benchmarks are not a good source of information for estimating resource requirements for future projects, as they may not account for the specific characteristics and needs of each organization. The budgeted forecast for the next financial year is not a good source of information for estimating resource requirements for future projects, as it may not be based on accurate or realistic assumptions. References:
* CISA Review Manual, 27th Edition, pages 465-4661
* CISA Review Questions, Answers & Explanations Database,Question ID: 263