正解:C
* Definition of ADM Phase G - Implementation Governance:
* ADM Phase G, Implementation Governance, is a phase in the TOGAF Architecture Development Method (ADM) focused on ensuring that the implementation of architecture projects aligns with the target architecture.
* Objectives of Implementation Governance:
* The primary objective is to provide architectural oversight for the implementation process.
* This involves ensuring that the projects and solutions being implemented conform to the defined target architecture.
* It includes monitoring compliance, managing changes, and providing governance to support successful implementation.
* Explanation of Correct answer:
* Option A, " To ensure that the enterprise ' s Architecture Capability meets current requirements, " is more related to the Preliminary Phase or Phase A (Architecture Vision).
* Option B, " To establish the value realization process, " pertains more to Phase H (Architecture Change Management) where value realization and benefits tracking are key activities.
* Option D, " To assess the performance of the architecture and make recommendations for change, " is primarily related to Phase H.
* Option C, " To ensure that implementation projects conform with the Target Architecture, " is the correct objective of Phase G. This phase is specifically designed to oversee the implementation, ensuring alignment with the target architecture and managing any deviations or changes.