数名の開発者が年次評価を終え、年次ボーナスを受け取った後、辞職を申し出ました。プロジェクトマネージャーは、プロジェクトの期限までに全ての開発者の代わりを見つけることができません。
プロジェクトマネージャーは何をすべきでしょうか?
正解:D
According to the PMBOK Guide, the project manager should analyze the impact of the developers' resignation on the project scope, schedule, cost, quality, and risk, and inform the relevant stakeholders about the situation and the possible options to address it. This is part of the Manage Team process, which involves tracking team member performance, providing feedback, resolving issues, and managing changes to optimize project performance. By analyzing the impact and informing the stakeholders, the project manager can facilitate collaborative decision making and ensure alignment of expectations and objectives. References:
(Professional in Business Analysis Reference Materials source and documents) PMBOK Guide, 6th edition, Chapter 9, Section 9.4, Manage Team PMP Exam Prep, 10th edition, Rita Mulcahy, Page 357, Manage Team