正解:D
This question belongs to the People domain because it focuses on stakeholder alignment, conflict resolution, and negotiation. PMI guidance on managing conflicting expectations emphasizes addressing conflict early, understanding the motivations behind stakeholder positions, and using negotiation to reach workable agreement. When stakeholder requirements conflict, the project manager should not postpone the issue or leave the decision entirely to the team. Instead, the project manager should work directly with the involved stakeholders to negotiate a common understanding and agreed priority.
Option A escalates too soon before the project manager has attempted resolution at the appropriate level.
Option B allows the conflict to remain unresolved and may create more confusion later. Option C is inappropriate because requirement priority among stakeholders is not something the project team should decide on its own. PMI-style leadership favors facilitation, negotiation, and expectation management to align stakeholders and protect project outcomes. Therefore, the best answer is to negotiate a common agreement with the involved stakeholders regarding the requirements.