IT 開発プロジェクトの開始時に、主要なリスクが特定および評価され、リスク所有者が任命されました。6 か月後、IT 開発チームは、プロジェクトが予算を大幅に超過し、予定どおりに完了せず、主要な担当者が組織を離れたと報告しました。将来のプロジェクトのために改善すべきリスク管理慣行は次のうちどれですか?
正解:C
In the context of internal auditing and risk management, the situation described involves the identification of key risks at the beginning of the IT development project, with risk owners appointed. However, the project later faces significant issues such as being over budget, delays, and loss of key personnel. These issues indicate that the ongoing management and oversight of identified risks were insufficient.
Risk monitoring is the continuous process of tracking and evaluating the performance and changes in the risk environment. Effective risk monitoring ensures that risk responses are executed as planned, emerging risks are identified, and necessary adjustments are made. The failure to stay on budget, meet deadlines, and retain key personnel suggests that there were lapses in regularly reviewing and updating the risk management plan and responses as the project progressed. Therefore, the risk management practice that should be improved for future projects is risk monitoring.
References:
* Institute of Internal Auditors (IIA), "Risk Management and Internal Audit: Forging a Collaborative Alliance"
* ISO 31000:2018 Risk Management - Guidelines