プロジェクト マネージャーは、必要な IT 機器の納入が遅れるとの連絡を受けました。どっち プロジェクトマネージャーが取るべき最初のステップは次のとおりですか?
正解:A
The project manager should make an impact assessment after being informed that the delivery of required IT equipment will be delayed. An impact assessment is a process of analyzing and evaluating how a change or an issue may affect the scope, schedule, cost, quality, or risks of a project. An impact assessment can help to determine the severity and implications of the delay on the project objectives and deliverables and identify any possible alternatives or corrective actions to minimize or avoid its negative effects.