データセンターの建設中であり、プロジェクトマネージャーは身体的傷害に関連するリスクに対処したいと考えています。このシナリオに最適なリスク対応方法は次のうちどれですか?
正解:C
In the context of construction projects, physical injuries are a significant risk. The most effective risk response method in this scenario is mitigation, which involves taking proactive steps to reduce the likelihood or impact of the risk. Training construction workers on safety protocols and procedures is a direct way to mitigate the risk of physical injuries.
According to the CompTIA Project+ PK0-005 exam objectives, under Domain 1.4: Given a scenario, perform risk management activities, mitigation is a key risk response strategy. The official objectives state:
"Develop risk response plans, including mitigation strategies to reduce the likelihood or impact of risks." CompTIA Project+ PK0-005 Exam Objectives By providing proper training, the project manager actively reduces the risk, aligning with best practices in risk management.