正解:D
In a RACI chart, which stands for Responsible, Accountable, Consulted, and Informed, the best practice is to have only one person accountable for each task to ensure clear ownership and avoid confusion. The image shows that three different stakeholders (Stakeholders 2, 4, and 6) are marked as accountable ('A') for Project Task 1, which is not recommended as it can lead to accountability issues and dilute the clarity of who is ultimately answerable for the task's completion. References: Best practices in project management and RACI chart guidelines.