正解:A
During PI Planning, teams are expected to create draft PI Objectives that summarize the business value they intend to deliver. However, a common anti-pattern occurs when teams spend too much time analyzing each Story instead of focusing on higher-level outcomes.
The goal of draft objectives is to express intent, alignment, and expected value-not to finalize every technical detail or task. Over-analyzing individual stories during PI Planning slows progress, distracts from collaboration with other teams, and limits the time available for identifying dependencies and risks.
From SAFe guidance:
"Teams should avoid excessive analysis of stories during PI Planning. The focus should be on creating draft objectives that align with business value and ART goals." Thus, the correct answer is A. Too much time is spent analyzing each Story, as it prevents the team from maintaining the right level of planning abstraction.