正解:D
The correct answer is D because PRINCE2 expects communication to be appropriate to stakeholder needs, not identical for everyone. Different stakeholders need different information, at different times, in different levels of detail, and through different channels.
Option A is incorrect because sending the same information to all stakeholders may overload some people and under-inform others. Option B is too narrow because team manager reporting helps monitor work progress, but it does not ensure effective communication across the whole project ecosystem. Option C is also too narrow because communication should not only focus on standard messages or key influencers; it should be planned around stakeholder needs.
PRINCE2 guidance supports identifying and consulting stakeholders to understand their communication needs and then defining the communication approach, including procedure, tools, timing, roles, and responsibilities. PRINCE2 also emphasizes an effective strategy for managing communication flows to and from stakeholders.