正解:C
According to the 'defined roles and responsibilities' principle in PRINCE2, three categories of stakeholder interest need to be represented in the project management team: business (represented by the Executive), user (represented by the Senior User), and supplier (represented by the Senior Supplier). This ensures that the key perspectives on the project's outputs, outcomes, and processes are fully integrated into decision-making and governance structures.References: PRINCE2Foundation ManualAccording to the 'defined roles and responsibilities' principle in PRINCE2, three categories of stakeholder interest need to be represented in the project management team: business (represented by the Executive), user (represented by the Senior User), and supplier (represented by the Senior Supplier). This ensures that the key perspectives on the project's outputs, outcomes, and processes are fully integrated into decision-making and governance structures.References: