金融機関の経営陣は、運用上のリスクを受け入れ、その結果、重要な監視プロセスを一時的に停止することになりました。この状況で情報セキュリティ管理者が最も懸念すべきことは、次のうちどれですか?
正解:C
Comprehensive and Detailed Explanation = The impact on the risk culture is the greatest concern for the information security manager, because it reflects the attitude and behavior of the organization towards risk management. If management accepts an operational risk that compromises a critical monitoring process, it may indicate a lack of awareness, commitment, or accountability for risk management. This may erode the trust and confidence of the stakeholders, regulators, and customers, and expose the organization to further risks. The impact on compliance risk, the inability to determine short-term impact, and the deviation from risk management best practices are also important, but they are secondary to the impact on the risk culture.
Reference = CISM Review Manual 15th Edition, page 48. CISM Review Questions, Answers & Explanations Database - 12 Month Subscription, question ID 421.