The following questions both of No.15 and No.46 are same but the answer does not match, which answer is correct? The answer is B but the answering explanation is incoherent.
NO.15 When scoping a risk assessment, assets need to be classified by: (A). sensitivity and criticality. (B). threats and opportunities (C). likelihood and impact (D). redundancy and recoverability. Answer: B
NO.46 When scoping a risk assessment, assets need lo be classified by (A). redundancy and recoverability (B). sensitivity and criticality. (C). threats and opportunities (D). likelihood and impact. Answer: B
最新のコメント (最新のコメントはトップにあります。)
The following questions both of No.15 and No.46 are same but the answer does not match, which answer is correct?
The answer is B but the answering explanation is incoherent.
NO.15 When scoping a risk assessment, assets need to be classified by:
(A). sensitivity and criticality.
(B). threats and opportunities
(C). likelihood and impact
(D). redundancy and recoverability.
Answer: B
NO.46 When scoping a risk assessment, assets need lo be classified by
(A). redundancy and recoverability
(B). sensitivity and criticality.
(C). threats and opportunities
(D). likelihood and impact.
Answer: B