正解:C
The best answer is C. Qualitative risk analyses have not been updated.
ISACA guidance describes the risk register as a living document that should be regularly reviewed and amended so management has an up-to-date picture of risk when making decisions. If qualitative risk analyses are not updated, the project may be working from outdated assumptions about probability, impact, and priority, which undermines the entire risk management process.
Option A is a concern, but issue tracking is not as central to project risk management as keeping risk analysis current. Option B is not inherently a weakness because effective risk management does not depend on a specific software tool. Option D is a governance concern, but stale risk analysis more directly damages the organization's ability to identify, assess, prioritize, and respond to project risk.
References (Official ISACA):
* ISACA Journal, Mitigating Technical Vulnerabilities With Risk Assessment - the risk register is a living document that should be regularly reviewed and amended.
* ISACA, Making Risk Management for Agile Projects Effective - risk registers are updated throughout the project lifecycle.