正解:B
EVA is a project management technique that measures the performance of a project by comparing the actual work completed, the actual costs incurred, and the planned costs for the work scheduled. EVA can help determine if the project is on track, ahead of schedule, or behind schedule, and if the project is under budget, over budget, or on budget. EVA can also help forecast the final cost and schedule of the project based on the current performance.